A and B complete a work in 6 days. A alone can do it in 10 days. If both together can do the work in how many days?
View Options
A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it?
View Options
A and B can do a piece of work in 12 days and 16 days respectively. Both work for 3 days and then A goes away. Find how long will B take to complete the remaining work?
View Options
A can do a piece of work in 40 days; B can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. C alone can do the whole work in?
View Options
A and B can do a piece of work in 7 days. With the help of C they finish the work in 5 days. C alone can do that piece of work in?
View Options
A can do a piece of work in 12 days. When he had worked for 2 days B joins him. If the complete work was finished in 8 days. In how many days B alone can finish the work?
View Options
A and B together can do a work in 6 days. If A alone can do it in 15 days. In how many days can B alone do it?
View Options
A, B and C can do a piece of work in 24, 30 and 40 days respectively. They start the work together but C leaves 4 days before the completion of the work. In how many days is the work done?
View Options
A, B and C can do a piece of work in 7 days, 14 days and 28 days respectively. How long will they taken, if all the three work together?
View Options
After working for 6 days, Ashok finds that only 1/3 rd of the work has been done. He employs Ravi who is 60% as efficient as Ashok. How many days more would Ravi take to complete the work?
View Options
A is twice as good a work man as B and together they finish the work in 14 days. In how many days A alone can finish the work?
View Options
A, B and C can do a work in 6, 8 and 12 days respectively doing the work together and get a payment of Rs.1800. What is B’s share?
View Options
If A, B and C together can finish a piece of work in 4 days. A alone in 12 days and B in 18 days, then C alone can do it in?
View Options
5 men and 12 boys finish a piece of work in 4 days, 7 men and 6 boys do it in 5 days. The ratio between the efficiencies of a man and boy is?
View Options
9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days?