Consider the following statements :A critical activity in a CPM network has1. The longest duration of all activities2. zero total float3. zero for float4. The shortest duration of all activitieswhich one of the statements given above are correct ?

( 5 )  .  1 Rating  .  16 Attempts
48 views   .  0 comments  .   . 

Download Solution PDF
  1.  1 and 2

  2.  1 and 3

  3.  2 and 3

  4.  3 and 4