A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time,each persons now working 9 hours a day?

( 5 )  .  1 Rating  .  1 Attempts
23 views   .  1 comments  .   . 

Download Solution PDF
  1.  160

  2.  150

  3.  24

  4.  56